1. | Analysis of INA Petrokemija Kutina, Croatia Ammonia - 2 and Urea Plant turbomachinery vibrational and mechanical condition during steady state operation and shutdown before overhaul TC21101+C21101LP+HP + SM21101, TC 21102+C21102LP+HP, TC21103+C1103LP+HP, TC21105 + C21105LP+HP and T22112 + C22112LP +SM22112 + C22112HP) - 17 machines | 1994 |
---|---|---|
2. | Analysis of INA Petrokemija Kutina, Croatia Ammonia - 2 and Urea Plant turbomachinery vibrational and mechanical condition during startup and steady operation after overhaul (TC21101+C21101LP+HP+SM21101, TC 21102+C21102LP+HP, TC21103+C1103LP+HP, TC21105 + C21105LP+HP and T22112 + C22112LP +SM22112 + C22112HP) - 17 machines | 1994 |
3. | Analysis of INA Petrokemija Kutina, Croatia TP 21153 turbine and P 21153 pump vibration behavior and condition | 1995 |
4. | Analysis of INA Petrokemija Kutina, Croatia Ammonia - 2 and Urea Plant turbomachinery vibrational and mechanical condition during steady state operation and shutdown before overhaul TC21101+C21101LP+HP + SM21101, TC 21102+C21102LP+HP, TC21103+C1103LP+HP, TC21105 + C21105LP+HP and T22112 + C22112LP +SM22112 + C22112HP) - 17 machines | 1995 |
5. | Analysis of INA Petrokemija Kutina, Croatia Ammonia - 2 and UREA plant turbomachines vibration condition included in predictive maintenance program (20 turbines, 14 compressors, 24 pumps, 2 hydro turbines, 3 fans) | 1995 |
6. | Analysis of INA Petrokemija Kutina, Croatia Ammonia - 2 and UREA plant turbomachines vibration condition included in predictive maintenance program (20 turbines, 14 compressors, 24 pumps, 2 hydro turbines, 3 fans) | 1995 |
7. | Analysis of INA Petrokemija Kutina, Croatia Ammonia - 2 plant turbomachines vbiration condition and behavior during plant startup (TC21101+C21101LP+HP + SM21101, TC21102+C21102LP+HP, TC21103+C1103LP+HP, TC21105+C21105LP+HP | 1995 |
8. | Analysis of INA Petrokemija Kutina, Croatia Ammonia - 2 and UREA plant turbomachines vibration condition included in predictive maintenance program (20 turbines, 14 compressors, 24 pumps, 2 hydro turbines, 3 fans) | 1995 |
9. | Analysis of INA Petrokemija Kutina, Croatia Ammonia - 2 and UREA plant turbomachines vibration condition included in predictive maintenance program (20 turbines, 14 compressors, 24 pumps, 2 hydro turbines, 3 fans) | 1995 |
10. | Analysis of INA Petrokemija Kutina, Croatia Amonijak - 2 plant sintesys compressor turbotrain TC+C 21103, P 21143,P 21143 A,TP 21143, PM 21143, P 21153,P 21153 A, TP 21153, PM 21153 vibration condition | 1995 |
11. | Analysis of INA Petrokemija Kutina, Croatia Ammonia - 2 plant ammonia cooling compressor turbotrain TC+C 21105LP+HP and P 21145,P21145A, TP 21145, PM 21145 | 1995 |
12. | Analysis of vibration condition of turbotrain TB +B21101 in Ammonia- 2 plant of INA Petrokemija Kutina, Croatia | 1995 |
13. | Vibration behavior and condition analysis of turbotrain TP + in Ammonia - 2 plant of INA Petrokemija Kutina, Croatia | 1995 |
14. | Vibration condtion and behavior analysis of turbotrain TP +P21104A in Ammonia - 2 plant of INA Petrokemija Kutina, Croatia | 1995 |
15. | Vibration condition and behavior analysis of turbotrain TB +B 21101 in Ammonia - 2 plant of INA Petrokemija Kutina, Croatia nakon zamjene rotora turbine | 1995 |
16. | Analysis of vibration and operational problem of the gearbox SR +P21104 A and turbotrain TP 21104A in Ammonia - 2 plant of INA Petrokemija Kutina, Croatia | 1995 |
17. | Vibration condition and behavior analysis of gearbox SR +P21104 A and turbotrain TP 21104A in INA Petrokemija Kutina, Ammonia-2 plant after repair | 1995 |
18. | Analysis of INA Petrokemija Kutina, Croatia Ammonia-2 plant hydroturbine THP 21107A vibration condition and behavior | 1995 |
19. | Vibration condition and behavior analysis of turbotrain TP +P21107B in Ammonia-2 plant of INA Petrokemija Kutina, Croatia | 1995 |
20. | Analysis of vibration condition of turbine, gearbox and pump TP+SR+P 21107B in INA Petrokemija Kutina, Amonijak plant | 1995 |
21. | Vibration analysisof condition and behavior of turbine, gearbox and pump TP+SR+P 21107B in INA Petrokemija Kutina, Ammonia-2 plant after turbine and gearbox revision | 1995 |
22. | Analysis of vibration behavior and condition of turbine TP 21107B in INA Petrokemija Kutina, Ammonia-2 plant | 1995 |
23. | Vibration condition and behavior analysis of Urea plant-2 CO2 compressor turbotrain TC+C 2211LP+HP + SM 221122 in INA Petrokemija Kutina, Croatia | 1995 |
24. | Analysis of vibration condition and behavior of Nitric acid 2 turbotrain in INA Petrokemija Kutina, Croatia | 1995 |
25. | Vibration condition and behavior analysis of turbotrains TP +P21108A and TP+P 21108B in Ammonia-2 plant of INA Petrokemija Kutina, Croatia | 1995 |
26. | Vibration condition and behavior analysis of turbine and gearbox TP+SR 21107B in Ammonia-2 plant of INA Petrokemija Kutina, Croatia after repairs | 1995 |
27. | Analysis of vibration condition and behavior of turbine TP 21107B in Ammonia-2 plant of INA Petrokemija Kutina, Croatia | 1996 |
28. | Analysis of vibration problem of Woodward governor on turbine TP 21107 A in Ammonia-2 plant of INA Petrokemija Kutina, Croatia | 1996 |
29. | Vibration condition and behavior analysis of turbotrain TP +P21107A in Ammonia-2 plant of INA Petrokemija Kutina, Croatia after turbine overhaul | 1996 |
30. | Analysis of Nitric Acid turbotrain (steam turbine+axial air compressor+Nitric gases centrifugal compressor + gas expander) vibration condition and behavior, INA Petrokemija Kutina, Croatia | 1996 |
31. | Vibration condition and behavior analysis of feed water turbotrain TP +SR 211014A+P21104A in Ammonia-2 plant of INA Petrokemija Kutina, Croatia | 1996 |
32. | Analysis of vibration condition ans problem of synthesis gas compressor turbotrain (TC211013+C21103LP+HP) in Ammonia-2 plant of INA Petrokemija Kutina, Croatia | 1996 |
33. | Analysis of INA Petrokemija Kutina, Croatia Ammonia - 2 and UREA plant turbomachines vibration condition included in predictive maintenance program (20 turbines, 14 compressors, 24 pumps, 2 hydro turbines, 3 fans) | 1996 |
34. | Analysis of INA Petrokemija Kutina, Croatia Ammonia - 2 and UREA plant turbomachines vibration condition included in predictive maintenance program (20 turbines, 14 compressors, 24 pumps, 2 hydro turbines, 3 fans) | 1996 |
35. | Analysis of INA Petrokemija Kutina, Croatia Ammonia - 2 and UREA plant turbomachines vibration condition included in predictive maintenance program (20 turbines, 14 compressors, 24 pumps, 2 hydro turbines, 3 fans) | 1996 |
36. | Analysis of INA Petrokemija Kutina, Croatia Ammonia - 2 and UREA plant turbomachines vibration condition included in predictive maintenance program (20 turbines, 14 compressors, 24 pumps, 2 hydro turbines, 3 fans) | 1996 |
37. | Analysis of INA Petrokemija Kutina, Croatia Ammonia - 2 and UREA plant turbomachines vibration condition included in predictive maintenance program (20 turbines, 14 compressors, 24 pumps, 2 hydro turbines, 3 fans) | 1996 |
38. | Analysis of INA Petrokemija Kutina, Croatia Ammonia - 2 and UREA plant turbomachines vibration condition included in predictive maintenance program (20 turbines, 14 compressors, 24 pumps, 2 hydro turbines, 3 fans) | 1996 |
39. | Analysis of INA Petrokemija Kutina, Croatia Ammonia - 2 and UREA plant turbomachines vibration condition included in predictive maintenance program (20 turbines, 14 compressors, 24 pumps, 2 hydro turbines, 3 fans) | 1996 |
40. | Analysis of turbotrain TP+SR+P+THP 21107B vibration problem in Ammonia Plant-2 (INA Petrokemija Kutina, Croatia) | 1997 |
41. | Vibration condition and behavior analysis of turbine TP+P+THP 21107A in Ammonia-2 plant of INA Petrokemija Kutina, Croatia during steady state operation | 1997 |
42. | Analysis of vibration condition ans problem of synthesis gas compressor turbotrain (TC211013+C21103LP+HP) in Ammonia-2 plant of INA Petrokemija Kutina, Croatia | 1997 |
43. | Analysis of Ammonia Plant-2 feed water pump turbotrain (TP+SR+P 21104)vibration condition and behavior (INA-Petrokemija Kutina, Croatia) during steady state operation | 1997 |
44. | Analysis of Ammonia Plant-2 feed water pump turbotrain (TP+SR+P 21104A)vibration condition and behavior (INA-Petrokemija Kutina, Croatia) during steady state operation | 1997 |
45. | Vibrational behavior analysis of INA Petrokemija Kutina, Croatia Amonijak - 2 plant machines included in predictive maintenance program (18 turbines, 12 compressors, 23 pumps, 2 hydro turbines, 3 fans) | 1997 |
46. | Analysis of ibration condition of Ammonia and Urea Plant-2 turbomachinery oil consol machines (Petrokemija Kutina,Croatia) during steady state operation (7 turbines + 7 pumps) | 1997 |
47. | Troubleshooting of Ammonia Plant-2 air compressor turbotrain TC+SM+ C 21101LP+HP (INA Petrokemija Kutina, Croatia) high vibration problem and disturbances | 1997 |
48. | Vibration condition and behavior analysis Ammonia Plant-2 air compressor turbotrain TC+SM+ C 21101LP+HP ( INA Petrokemija Kutina, Croatia) during no disturbance operation | 1997 |
49. | Analysis of of Ammonia Plant-2 air compressor turbotrain TC+SM+C 21101LP+HP (INA Petrokemija Kutina, Croatia) during startup and steady state operation | 1997 |
50. | Analysis of of Ammonia Plant-2 gas compressor turbotrain TC+C 21102LP+HP (INA Petrokemija Kutina, Croatia) during startup and steady state operation | 1997 |
51. | Analysis of Ammonia Plant-2 air compressor gearbox SM 21101 vibration problem (INA Petrokemija Kutina, Croatia) | 1998 |
52. | Analysis of mechanical (vibrational) condition of Ammonia Plant-2 sysnthesis gas turbotrain turbine TC 21103 (INA Petrokemija Kutina, Croatia) after inspection from 19.06. to 23.06.1997. | 1997 |
53. | Analysis of of Ammonia Plant-2 synthesis gas compressor turbotrain TC+C 21103LP+HP (INA Petrokemija Kutina, Croatia) during startup and steady state operation | 1997 |
54. | Analysis of Ammonia Plant-2 refrigerant compressor turbotrain TC+C21105LP+HP vibrationcondition and behavior (INA Petrokemija Kutina, Croatia) | 1997 |
55. | Vibration condition and behavior analysis of turbotrain TB+SR+B21101 in Ammonia Plant-2 of INA Petrokemija Kutina, Croatia during steady state operation | 1997 |
56. | Vibration condition and behavior analysis of turbotrain TB +SR+B21102 in Ammonia Plant-2 of INA Petrokemija Kutina, Croatia during steady state operation | 1997 |
57. | Analysis of vibration condition and behavior of Urea Plant-2 turbotrain TC+ SM+C 22112LP+HP in INA Petrokemija Kutina, Croatia during startup and steady state operation | 1997 |
58. | Analysis of vibration condition and behavior Methanol Plant sysnthesis gas compressor (GT201 + C201+202) during startup and loading (Nafta Lendava, Slovenia) | 1998 |
59. | Power Plant Tuzla (BiH) 200 MW turbogenerator (Unit 5) vibration condition and behavior | 1998 |
60. | Power Plant Tuzla (BiH) 215 MW turbogenerator (Unit 6) vibration condition and behavior | 1998 |
61. | Power Plant Tuzla (BiH) 200 MW turbogenerator (Unit 5) vibration condition and behavior | 1998 |
62. | Analysis of vibration condition of Ammonia Plant turbotrains (TC+SM+C21101LP+HP,TC+C21102LP+HP, TC+C21103LP+HP and TC+C21105LP+HP) in INA Petrokemija Kutina, Croatia | 1998 |
63. | Analysis of vibration condition and behavior of Nitric Acid-2 Plant turbotrain (steam turbine+axial air compressor+gas centrifugal compressor+gas expander) in INA Petrokemije Kutina, Croatia | 1998 |
64. | Ammonia Plant-2 gas compressor turbotrain (TC+C 21102LP+HP) vibration condition and behavior analysis (INA Petrokemije Kutina, Croatia) during steady state operation and shutdown for overhaul | 1998 |
65. | Ammonia Plant-2 air compressor turbotrain (TC+SM+C 21101LP+HP) vibration condition and behavior analysis (INA Petrokemije Kutina, Croatia) during steady state operation and shutdown for overhaul | 1998 |
66. | Ammonia Plant-2 synthesis compressor turbotrain (TC+C 21103LP+HP) vibration condition and behavior analysis (INA Petrokemije Kutina, Croatia) during steady state operation and shutdown for overhaul | 1998 |
67. | Ammonia Plant-2 ammonia refrigerant compressor turbotrain (TC+C 21105LP+HP) vibration condition and behavior analysis (INA Petrokemije Kutina, Croatia) during steady state operation and shutdown for overhaul | 1998 |
68. | Analysis of vibration condition of Nitric Acid-1 turbotrin 1 (INA Petrokemije Kutina, Croatia) | 1998 |
69. | Urea Plant-2 turbotrain (TC+SM+C 22112LP+HP) vibration condition and behavior analysis (INA Petrokemije Kutina, Croatia) during steady state operation and shutdown for overhaul | 1998 |
70. | Ammonia Plant-2 air compressor turbotrain (TC+SM+C 21101LP+HP) vibration condition and behavior analysis (INA Petrokemije Kutina, Croatia) during startup, loading and steady state operation after overhaul | 1998 |
71. | Ammonia Plant-2 gas compressor turbotrain (TC+C 21102LP+HP) vibration condition and behavior analysis (INA Petrokemije Kutina, Croatia) during startup, loading and steady state operation after overhaul | 1998 |
72. | Ammonia Plant-2 synthesis compressor turbotrain (TC+C 21103LP+HP) vibration condition and behavior analysis (INA Petrokemije Kutina, Croatia) during startup, loading and steady state operation after overhaul | 1998 |
73. | Ammonia Plant-2 ammonia refrigerant compressor turbotrain (TC+C 21105LP+HP) vibration condition and behavior analysis (INA Petrokemije Kutina, Croatia)during startup, loading and steady state operation after overhaul | 1998 |
74. | Urea Plant-2 turbotrain (TC+SM+C 22112LP+HP) vibration condition and behavior analysis (INA Petrokemije Kutina, Croatia) during startup, loading and steady state operation after overhaul | 1998 |
75. | Power Plant Tuzla (BiH) 200 MW turbogenerator (Unit 5) vibration condition and behavior | 1998 |
76. | Power Plant Tuzla (BiH) 200 MW turbogenerator (Unit 4) vibration condition and behavior | 1998 |
77. | Power Plant Tuzla (BiH) 100 MW turbogenerator (Unit 3) vibration condition and behavior | 1998 |
78. | Analysis of vibration condition and behavior Methanol Plant sysnthesis gas compressor (GT201 + C201+202) during steady stateoperation and shutdown (Nafta Lendava, Slovenia) | 1998 |
79. | Analysis of vibration condition and behavior Methanol Plant sysnthesis gas compressor (GT201 + C201+202) during startup and loading (Nafta Lendava, Slovenia) during startup | 1998 |
80. | Vibration condition and behavior analysis of Siemens 5 MW turbogenerator in Papirnica Radece (Paper Mill), Radeče, Slovenia, during steady state operation | 1999 |
81. | Power Plant Šoštanj (Slovenia) Unit 5 345 MW turbogenerator vibration analysis during steady state operation | 1999 |
82. | Power Plant Tuzla (BiH) 215 MW turbogenerator (Unit 6) vibration condition and behavior analysis | 1999 |
83. | Vibration condition and behavior analysis of 345 MW turbogenerator (Unit 5) of Power Plant (PP) Šoštanj, Slovenia, during steady state operation | 1999 |
84. | Ethylen Plant crack gas compressor turbotrain R1 (steam turbine+LP compressor+gear box+HP compressor vibration condition and behavior analysis (HIP Petrohemija Pancevo, Serbia and Montenegro) during steady state operation | 1999 |
85. | Ethylen Plant prophylen compressor turbotrain R2 (steam turbine+compressor) vibration condition and behavior analysis (HIP Petrohemija Pancevo, Serbia and Montenegro) during steady state operation | 1999 |
86. | Ethylen Plant ethylen compressor turbotrain R3 (steam turbine+compressor) vibration condition and behavior analysis (HIP Petrohemija Pancevo, Serbia and Montenegro) during steady state operation | 1999 |
87. | Vibration condition and behavior analysis of Etilen plant turbotrain R3 in HIP Petrohemija Pancevo, Serbia and Montenegro during steady state operation | 1999 |
88. | Vibration condition and behavior analysis of Etilen plant turbotrain R1 in HIP Petrohemija Pancevo, Serbia and Montenegro during steady state operation | 1999 |
89. | Vibration condition and behavior analysis of Etilen plant turbotrain R2 in HIP Petrohemija Pancevo, Serbia and Montenegro during steady state operation | 1999 |
90. | Vibration condition and behavior analysis of Etilen plant turbotrain R3 in HIP Petrohemija Pancevo, Serbia and Montenegro during steady state operation | 1999 |
91. | Vibration condition and behavior analysis of Etilen plant compressor turbotrain R3 HIP Petrohemija Pancevo, Serbia and Montenegro after startup | 1999 |
92. | Vibration condition and behavior analysis of Etilen plant turbotrain R1 in HIP Petrohemija Pancevo, Serbia and Montenegro, during startup, loading and steady state operation after overhaul | 1999 |
93. | Vibration problem analysis of Etilen plant oil pump turbotrain R1 in HIP Petrohemija Pancevo, Serbia and Montenegro Etilen plant | 1999 |
94. | Power Plant Tuzla (BiH) 200 MW turbogenerator (Unit 5) vibration condition and behavior | 2000 |
95. | Vibration condition and behavior analysis of Etilen plant turbotrain R1 in HIP Petrohemija Pančevo, Serbia and Montenegro, during steady state operation | 2000 |
96. | Vibration condition and behavior analysis of Etilen plant turbotrain R2 in HIP Petrohemija Pančevo, Serbia and Montenegro, during steady state operation | 2000 |
97. | Vibration condition and behavior analysis of Etilen plant turbotrain R3 in HIP Petrohemija Pančevo, Serbia and Montenegro, during steady state operation | 2000 |
98. | Analysis of vibration condition of Etilen plant boiler B fan in HIP Petrohemija Pancevo, Serbia and Montenegro, during steady state operation | 2000 |
99. | Vibration condition analysis of Etilen plant feed pump turbotrain P 1001A in HIP Petrohemija Pancevo, Serbia and Montenegro Etilen plant | 2000 |
100. | Vibration condition analysis of Etilen plant feed water pump turbotrain P 1001B in HIP Petrohemija Pancevo, Serbia and Montenegro | 2000 |
101. | Vibration condition analysis of Etilen plant feed water pump turbotrain P 1001C in HIP Petrohemija Pancevo, Serbia and Montenegro | 2000 |
102. | Analysis of vibration condition and behavior of 50 MW turbogeneratora (Unt 3) of Termoelektrana Toplarna Ljubljana, Slovenia, during steady state operation, unloading and shutdown for overhaul | 2000 |
103. | Vibration condition and behavior analysis of 30 MW turbogenerator (Unit 1) in Termoelektrana Toplarna Ljubljana, Slovenia during steady state operation | 2000 |
104. | Complex vibration problem analysis of Refinery Sisak Power Plant's 30 MW turbogenerator during startup, steady state operation and shutdown (INA, Croatia) | 2000 |
105. | Vibration condition and behavior analysis of Methanol Plant synthesis compressor turbotrain (GT201 + C201+202) in Nafta Lendava, Slovenia, during steady state operation | 2000 |
106. | High vibration amplitudes problem analysis of FCC Plant's turbine TGB 2501 in NIS Refinery Pancevo, Serbia and Montenegro, with recommendations for operation | 2000 |
107. | Vibration condition and behavior analysis of FCC Plant's turbine TGB 2301 and compressor GB 2301 in NIS-Refinery Pancevo, Serbia and Montenegro, with operation recommendations | 2000 |
108. | Analysis of vibration and mechanical condition of Ethylen Plant's turbotrains R1 and R2 in HIP Petrohemija Pancevo, Serbia and Montenegro, during steady state operation | 2000 |
109. | Vibration condition analysis of Ethylen Plant's turbotrain R2 in HIP Petrohemija Pancevo, Serbia and Montenegro, during steady state operation | 2000 |
110. | Vibration condition analysis of Ethylen Plant's turbotrain R2 in HIP Petrohemija Pancevo, Serbia and Montenegro, during steady state operation | 2000 |
111. | Analysis of FCC Plant turbine TGB 2301 and compressor GB 2301 problems in NIS-Refinery Pancevo, Serbia and Montenegro, during startup, steady state operation and shutdown with operation recommendations | 2000 |
112. | Analysis of vibration condition and behavior of Ethylen Plant's turbotrain R1 in HIP Petrohemija Pancevo, Serbia and Montenegro, after overhaul and demagnetization | 2000 |
113. | Vibration behavior analysis of turbotrain Ethylen Plant's R2 turbotrain in HIP Petrohemija Pancevo,Sewrbia and Montenegro, during startup and steady state operation with load increase | 2000 |
114. | Vibration condition and behavior analysis of Etilen plant turbotrain R3 in HIP Petrohemija Pančevo, Serbia and Montenegro, during steady state operation | 2000 |
115. | Vibration condition and behavior analysis of Methanol Plant synthesis compressor turbotrain (GT201 + C201+202) in Nafta Lendava, Slovenia, during steady state operation | 2001 |
116. | Vibration condition and behavior analysis of Power Plant's 7 MW turbogenerator in Nafta Lendava, Slovenia, during steady state operation | 2001 |
117. | Vibration condition and behavior analysis of Methanol Plant synthesis compressor turbotrain (GT201 + C201+202) in Nafta Lendava, Slovenia, during steady state operation and shutdown for overhaul | 2001 |
118. | Vibration condition analysis of cooling towers fans in Energetika plant of Nafta Lendava, Slovenia, during steady state operation and shutdown | 2001 |
119. | Vibration condition and behavior analysis of Power Plant's 7 MW turbogenerator in Nafta Lendava, Slovenia, during steady state operation and shutdown | 2001 |
120. | Vibration condition and behavior analysis of Power Plant's 7 MW turbogenerator in Nafta Lendava, Slovenia, during startup, loading and steady state operation | 2001 |
121. | Vibration condition and behavior analysis of Methanol Plant's synthesis compressor turbotrain (GT201 + C201+202) in Nafta Lendava, Slovenia, during startup, loading and steady state operation | 2001 |
122. | Analysis of vibration condition and behavior of Ethylen Plant's turbotrain R1 in HIP Petrohemija Pancevo, Serbia and Montenegro, after overhaul and demagnetization | 2001 |
123. | Vibration behavior analysis of Ethylen Plant's R2 turbotrain in HIP Petrohemija Pancevo, Serbia and Montenegro, during startup and steady state operation with load increase | 2001 |
124. | Vibration behavior analysis of Ethylen Plant's R3 turbotrain in HIP Petrohemija Pancevo, Serbia and Montenegro, during startup and steady state operation with load increase | 2001 |
125. | Balancing and vibration condition and behavior analysis of fan CM-102AX in Etan plant (Ivanic Grad) of INA-Naftaplian, Croatia | 2001 |
126. | Balancing and vibration condition and behavior analysis of fan CM-102BX 102AX in Etan plant (Ivanic Grad) of INA-Naftaplian, Croatia | 2001 |
127. | Balancing and vibrational behavior analysis of fan CM-103X 102AX in Etan plant (Ivanic Grad) of INA-Naftaplian, Croatia | 2001 |
128. | Balancing and vibration condition and behavior analysis of fan CM-701BX 102AX in Etan plant (Ivanic Grad) of INA-Naftaplian, Croatia | 2001 |
129. | Vibration condition and behavior analysis of 215 MW turbogenerator (Unit 6) in „Power plant Tuzla ", Tuzla, BiH, during steady state operation and shutdown with special analysis of high vibration levels problem on bearings no. 5 and 6 | 2001 |
130. | Anakysis of PP Tuzla's 200 MW turbogenerator (Unit 5) vibration condition and behavior (Tuzla, BiH), during steady state operation and shutdown | 2001 |
131. | Vibration condition and behavior analysis of pressure fan trains Ta1 and Ta2 in Clinical hospital Dubrava, Zagreb, Croatia | 2001 |
132. | Vibration condition and behavior analysis of suction fan trains Oa1 and Oa2 in Clinical hospital Dubrava, Zagreb, Croatia | 2001 |
133. | Vibrational behavior analysis of pressure fan trains Tb1 and Tb2 in Klinicka bolnica Dubrava, Zagreb, Croatia | 2001 |
134. | Vibrationcondition and behavior analysis of suction fan trains Ob1 and Ob2 in Clinical hospital Dubrava, Zagreb, Croatia | 2001 |
135. | Vibration condition and behavior analysis of pressure fan trains Tc1 and Tc2 in Clinical hospital Dubrava, Zagreb, Croatia | 2001 |
136. | Vibration condition and behavior analysis of suction fan trains Oc1 and Oc2 in Clinical hospital Dubrava, Zagreb, Croatia | 2001 |
137. | Vibration condition and behavior analysis of pressure fan trains Td1 and Td2 in Clinical hospital Dubrava, Zagreb, Croatia | 2001 |
138. | Vibration condition and behavior analysis of suction fan trains Od1 and Od2 in Clinical hospital Dubrava, Zagreb, Croatia | 2001 |
139. | Vibration condition and behavior analysis of pressure fan trains Te1 and Te2 in Clinical hospital Dubrava, Zagreb, Croatia | 2001 |
140. | Vibration condition and behavior analysis of pressure fan trains Tf1 and Tf2 in Clinical hospital Dubrava, Zagreb, Croatia | 2001 |
141. | Vibration condition and behavior analysis of suction fan trains Oef1 and Oef2 Clinical hospital Dubrava, Zagreb, Croatia | 2001 |
142. | Vibration condition and behavior analysis of pressure fan trains Tg1 and Tg2 in Clinical hospital Dubrava, Zagreb, Croatia | 2001 |
143. | Vibration condition and behavior analysis of suction fan trains Og1 and Og2 in Clinical hospital Dubrava, Zagreb, Croatia | 2001 |
144. | Vibration condition and behavior analysis of 215 MW turbogenerator (Unit 6) in „Power plant Tuzla ", Tuzla, BiH, during steady state operation | 2001 |
145. | Vibration condition analysis of Ethylen Plant's turbotrain R1 in HIP Petrohemija Pancevo, Serbia and Montenegro, during steady state operation | 2001 |
146. | Vibration condition analysis of Ethylen Plant's turbotrain R2 in HIP Petrohemija Pancevo, Serbia and Montenegro, during steady state operation | 2001 |
147. | Vibration condition analysis of Ethylen Plant's turbotrain R3 in HIP Petrohemija Pancevo, Serbia and Montenegro, during steady state operation | 2001 |
148. | Analysis of vibration condition of rotary screw compressor train C-160 A , Underground Gas Storage, PSP Okoli, INA-Naftaplina,Croatia | 2001 |
149. | Analysis of vibration condition of rotary screw compressor train C-160 B , Underground Gas Storage, PSP Okoli, INA-Naftaplina,Croatia | 2001 |
150. | Vibration condition and behavior analysis of turbotrain FCC Plant's turbotrain TGB+B 2501 in NIS-Refinery Pancevo, Serbia and Montenegro | 2001 |
151. | Power Plant Tuzla (BiH) 210 MW turbogenerator (Unit 5) vibration condition and behavior analysis | 2001 |
152. | Vibration condition and behavior analysis of turbotrain FCC Plant's turbotrain TGB+B 2501 in NIS-Refinery Pancevo, Serbia and Montenegro | 2001 |
153. | High vibration levels problem analysis of diesel engine in INA-Naftaplin, Ivanicko Graberje, Croatia | 2001 |
154. | Vibration condition and behavior analysis of 30 MW turbogenerator (Unit 1) in PP Šoštanj, Slovenia, during steady state operation at various loads and shutdown before overhaul | 2001 |
155. | Vibration condition and behavior analysis of 30 MW turbogenerator (Unit 2) in PP Šoštanj, Slovenia, during steady state operation at various loads and shutdown before overhaul | 2001 |
156. | Vibration condition and behavior analysis of 30 MW turbogenerator (Unit 1) in PP Šoštanj, Slovenia, during steady state operation during startup, loading and operation under various loads and shutdown after overhaul | 2001 |
157. | Vibration condition and behavior analysis of 30 MW turbogenerator (Unit 2) in PP Šoštanj, Slovenia, during steady state operation during startup, loading and operation under various loads and shutdown after overhaul | 2001 |
158. | Maeasurements and vibrational condition analysis of fan RDP in PP Šoštanj, Slovenia | 2001 |
159. | Analysisi andeExpert opinion on vibration condition and behavior of 345 MW turbogenerator (Unit 5) in PP Šoštanj, Slovenia with special analysis of high vibration levels problem on bearings no. 2 and 3 | 2001 |
160. | Vibration behavior analysis of 345 MW turbogenerator (Unit 5) in Power Plant (PP) Šoštanj, Slovenia, during startups on 04. and 05.11.2001. | 2001 |
161. | Analysis of Methanol Plant turbotrain GT201 + G201+202 vibration condition and behavior in Nafta Lendava, Slovenia during steady state operation and shutdown before overhaul | 2001 |
162. | Analysis of Power plant's 7 MW turbogenerator vibration condition and behavior in Nafta Lendava, Slovenia during steady state operation and shutdown for the overhaul | 2001 |
163. | Vibration condition and behavior analysis of Power Plant boiler fan train OE in Nafta Lendava, Slovenia during steady state operation | 2001 |
164. | Vibration condition and behavior analysis of turbine pump 2 train OE machines inPower Plant, Nafta Lendava, Slovenia during steady state operation | 2001 |
165. | Complex dana acquisition and analysis for finding root cause of high vibration levels on bearings no. 1 and 2 of 345 MW turbogenerator (Unit 5) n Power Plant Šoštanj, Slovenia | 2001 |
166. | Vibration condition and behavior analysis of Blower P1 machines on Formalin 1 Plant, Nafta Lendava, Slovenia during steady state operation | 2002 |
167. | Vibration condition and behavior analysis of Blower P2 machines on Formalin 1 Plant, Nafta Lendava, Slovenia during steady state operation | 2002 |
168. | Vibration condition and behavior analysis of Blower P2 machines on Formalin 1 Plant, Nafta Lendava, Slovenia during steady state operation after overhaul | 2002 |
169. | Vibration condition and behavior analysis of Blower P1 machines on Formalin 1 Plant, Nafta Lendava, Slovenia during steady state operation after overhaul | 2002 |
170. | Complex vibration condition and behavior analysis of 100 MW turbogenerator MW machines and foundations on Unit 5 in „PP Kakanj "Kakanj, B and H, during steady state operation with evaluation of fundation suitability for the new turbine instalation | 2002 |
171. | Analysis of vibration condition and behavior of Power Plant's 7 MW turbogenerator, Nafta Lendava, Slovenia during startup and steady state operation after overhaul | 2002 |
172. | Analysis of vibration condition and behavior of blower C-17 in Etan P lant, INA-Naftaplina, Ivanic Grad, Croatia during startup and steady state operation | 2002 |
173. | Analysis of vibration condition and and balancing of pressure fan TA1 section A in Clinic Hospital" Dubrava ", Zagreb, Croatia | 2002 |
174. | Analysis of vibration condition and and balancing of pressure fan TA2 section A in Clinic Hospital" Dubrava ", Zagreb, Croatia | 2002 |
175. | Analysis of the FCC Plant's turbotrain TGB+B 2501 high vibration problem, NIS-refinery Rafinerija Pancevo, Serbia and Montenegro | 2002 |
176. | FCC Plant's turbotrain TGB+B 2301 machines vibration condition and behavior analysis during steady state operation and shutdown before overhaul in NIS-refinery Pancevo, Serbia and Montenegro | 2002 |
177. | FCC Plant's turbotrain TGB+B 2501 machines vibration condition and behavior analysis during steady state operation and shutdown before overhaul in NIS-refinery Pancevo, Serbia and Montenegro | 2002 |
178. | Analysis of Vibration condition and behavior of 100 MW turbogenerator machines and foundations in blok 6 „PP Kakanj "Kakanj, B and H, during steady state operation and shutdown before overhaul | 2002 |
179. | FCC Plant's turbotrain TGB+B 2301 machines vibration condition and behavior analysis during startiup and steady state operation after overhaul in NIS-refinery Pancevo, Serbia and Montenegro | 2002 |
180. | FCC Plant's turbotrain TGB+B 2501 machines vibration condition and behavior analysis during startiup and steady state operation after overhaul in NIS-refinery Pancevo, Serbia and Montenegro | 2002 |
181. | Analysis of high vibration amplitudes problem on bearings no. 1 and 2 of 345 MW turbine(Unoit 5), Termoelektrarna (Power plant), Šoštanj Slovenia | 2002 |
182. | Analysis of turbine TGB 2501 high vibration levels problem on FCC plant, NIS-RefineryPancevo, Serbia and Montenegro during startup and steady state operation after overhaul | 2002 |
183. | Analysis of compressor B 2501 high vibration levels problem on FCC plant, NIS-Refinery Pancevo, Serbia and Montenegro after overhaul | 2002 |
184. | Analysis of compressor B 2301 high vibration levels problem on FCC plant, NIS-Refinery Pancevo, Serbia and Montenegro after overhaul | 2002 |
185. | Vibration condition and behavior analysis of gas turbogenerator machines on Ethan Plant (Ivanic Grad) INA-Naftaplina, Croatia | 2002 |
186. | Analysis of vibration condition and behavior of 70 MW gas turbine turbogenerator GT-1 in Termoelektrana-Toplana, Zagreb, Croatia | 2002 |
187. | Analysis of vibration condition and behavior of 70 MW gas turbine turbogenerator GT-2 in Termoelektrana-Toplana, Zagreb, Croatia | 2002 |
188. | Vibration condition and behavior analysis of turbogenerator 110 MW machines of „PP " Kakanj " Kakanj, B and H, during startup, losding and steady state operation | 2002 |
189. | Vibration condition and behavior analysis of 210 MW turbogenerator (Unit 5) in „Power plant Tuzla ", Tuzla, BiH, during steady state operation | 2002 |
190. | Analysis of aggravated vibrational condition and behavior of 210 MW turbogenerator machines in Power Plant Plomin, Plomin, Croatia | 2002 |
191. | Analysis of aggravated vibrational behavior of gas turbine of 110 MW turbogenerator GT-14 in Termoelektrarna Brestanica, Brestanica, Slovenia | 2002 |
192. | Vibration condition and behavior analysis of gas turbine 110 MW turbogenerator GT-14 in Termoelektrarna Brestanica, Brestanica, Slovenia after repairs | 2002 |
193. | Analysis of aggravated vibrational behavior of Unit 5 345 MW turbine in Termoelektrarna (Power Plant) Šoštanj, Slovenia | 2002 |
194. | Analysis of high vibration problem of turbogenerator 1 machines (gas turbine+gear box+generator) in Ethan Plant, INA-Naftaplin, Ivanic Grad, Croatia | 2002 |
195. | Analysis of 100 MW (Unit 3) turbogenerator (turbine+generator) brgs. 3 and 4 high vibrations problem after overhaul in august in blok 3, „Power Plant Tuzla“, Tuzla, B&H | 2002 |
196. | Analysis of vibration condition and behavior analysis of all 100 MW turbogenerator machines (Unit 3) in november, „Power Plant Tuzla“, Tuzla, B&H with special analysis of high vibration problem on bearing no. 1 and bearing modeling | 2002 |
197. | Vibration condition and behavior analysis of 200 MW turbogenerator machines (Unit 4) in „Power Plant Tuzla“, Tuzla, B&H after overhaul and reconstruction with creation of reference database of vibrational and other data | 2002 |
198. | Vibration condition and behavior analysis of all machines (gas turbine, gearbox, generator) of 110 MW turbogenerator GT-15, Termoelektrarna (Power plant) Brestanica, Slovenia | 2002 |
199. | Analysis of 345 MW turbinogenerator (Unit 5) high vibration levels and bearing no. 2 failure in Termoelektrarna (Power Plant) Šoštanj, Slovenia, with recommendations for bearing design modifications | 2002 |
200. | Analysis of the high vibration levels problem of blower C-17 B with rotor balancing in Ethan plant, INA-Naftaplin, Ivanic Grad, Croatia | 2003 |
201. | Vibration condition and behavior analysis of turbogenerator 2 machines, (gas turbine+gear box+generator) of Ethan Plant, INA-Naftaplin, Ivanic Grad, Croatia | 2003 |
202. | Predictive maintenance program (regular vibrodiagnostics) of 46 machines in Termoelektrarna (Power Plant ) Šoštanj, Slovenia | 2003 |
203. | Base vibration condition and behavior analysis of 46 machines in PP Šoštanj, Slovenia (turbogenerators 345 MW, 275 MW, 75 MW and 2X30 MW, feed pumps, fans,...) | 2003 |
204. | Vibration condition and behavior analysis of Unit 3 23 MW turbogenerator (gas turbine, gearbox , generator), Power Plant Brestanica, Slovenia | 2003 |
205. | Vibration condition and behavior analysis of turbogenerator 2 machines, (gas turbine+gear box+generator) of Ethan Plant, INA-Naftaplin, Ivanic Grad, Croatia | 2003 |
206. | Vibration condition and behavior analysis of blower C-17 in Ethan Plant, INA-Naftaplin, Ivanic Grad, Croatia | 2003 |
207. | Reference vibration condition and state analysis of reciprocating compressors on Ethan Plant, INA-Naftaplin, Ivanic Grad, Croatia | 2003 |
208. | Analysis of vibration condition and behavior of reciprocating compressor on Etan plant after modifications, INA-Naftaplina Ivanic Grad, Croatia | 2003 |
209. | Analysis of high vibration levels problem of FCC Plant turbocompressor GB 2501 in NIS-Refinery Pancevo, Serbia and Montenegro | 2003 |
210. | Vibration condition and behavior analysis of Unit 2 23 MW turbogenerator (gas turbine, gearbox , generator), Power Plant Brestanica, Slovenia | 2003 |
211. | Vibration condition and behavior analysis of 345 MW turbogenerator (Unit 5), Termoelektrarna (Power Plant) Šoštanj, Slovenia | 2003 |
212. | Vibration condition and behavior analysis of all machines (gas turbine, gearbox, generator) of 110 MW turbogenerator GT-14 in Termoelektrarna (Power plant) Brestanica, Slovenia | 2003 |
213. | Vibration condition and behavior analysis of all 200 MW turbogenerator (Unit 5) machines in „Power Plant Tuzla", Tuzla, BiH after overhaul and modernization with creation of reference database of vibrational and other data | 2003 |
214. | Analysis of vibration condition and behavior of 32 MW turbogenerator (turbine+generator) in TE-TOL, Ljubljana, Slovenia | 2003 |
215. | Vibration condition and behavior analysis of all 110 MW turbogenerator machines (gas turbine, gearbox, generator) GT-15 in PP Brestanica, Slovenia | 2004 |
216. | Vibration condition and behavior analysis of Unit 3 75 MW generator in Power Plant Šoštanj, Slovenia during complex generator's high vibration problem investigation and testing with load variations | 2004 |
217. | Vibration condition and behavior analysis of Unit 3 75 MW generator in Power Plant Šoštanj, Slovenia | 2004 |
218. | Vibration condition and behavior analysis of Unit 1 23 MW turbogenerator (gas turbine, gearbox , generator), Power Plant Brestanica, Slovenia | 2004 |
219. | Vibration condition and behavior analysis of Unit 2 23 MW turbogenerator (gas turbine, gearbox , generator), Power Plant Brestanica, Slovenia | 2004 |
220. | Vibration condition and behavior analysis of electro motor and gerbox of extruder in Plant DIOKI d.d. Zagreb, Croatia | 2004 |
221. | Analysis of vibrational condition and behavior of 210 MW turbogenerator (Unit 2) in Power Plant Plomin, Croatia | 2004 |
222. | Analysis of vibration condition and behavior of all 110 MW turbogenerator GT-14 machines (gas turbine+gear box+generator) in Power Plant Brestanica, Slovenia during start-up, steady state and shut-down after overhaul | 2004 |
223. | Analysis of vibration condition and behavior of 75 MW turbine and generator (Unit 3) in Power Plant Šoštanj, Slovenia, after overhaul | 2004 |
224. | Vibration condition and behavior analysis of 30 MW turbogenerator (turbine+generator) of Unit 1 in Power Plant Šoštanj, Slovenia before overhaul | 2004 |
225. | Vibration condition and behavior analysis of electromotor and fan on pressure train 2 of air-conditioning system G in KB Dubrava, Zagreb during steady state operation | 2004 |
226. | Vibration condition and behavior analysis of electromotor and fan on pressure train 1 of air-conditioning system G in KB Dubrava, Zagreb during steady state operation | 2004 |
227. | Vibration condition and behavior analysis of electromotor and fan on suction train 2 air-conditioning G KB Dubrava, Zagreb, croatia during steady state operation | 2004 |
228. | Vibrational behavior analysis and balancing of electromotor and fan on laundry system in KB Dubrava, Zagreb, Croatia | 2004 |
229. | Analysis of ibration condition and behavior of 3223 MW gas turbogenerator (turbine, gearbox, generator) of Unit 3 in Power Plant Brestanica, Brestanica, Slovenia | 2004 |
230. | Overhaul, balancing and vibration condition and behavior analysis of electro motor and fan in incinerator unit in KB Dubrava, Zagreb, Croatia | 2004 |
231. | Vibration condition and behavior analysis and balacing of pump Traint 807a in Ethan plant Ivanić Grad, INA-Naftaplina d.d. Zagreb, Croatia | 2004 |
232. | Analysis of vibration condition and behavior of 30 MW turbine and generator (Unit 1) in Power Plant Šoštanj, Slovenia during startup, loading and steady state operation after overhaul | 2004 |
233. | Analysis of vibration condition and behavior of 30 MW turbine and generator (Unit 2) in Power Plant Šoštanj, Slovenia during steady state operation, unloading and shutdown for overhaul | 2004 |
234. | Analysis of vibration condition and behavior of 30 MW turbine and generator (Unit 2) in Power Plant Šoštanj, Slovenia during startup, loading and steady state operation after overhaul | 2004 |
235. | Analysis of high vibration problem of FCC Plant turbotrain train GB 2501 in NIS-Refinery Pančevo, Serbia and Montenegro, | 2004 |
236. | Vibration condition and behavior analysis and balncing of fan in laundry unit of KB (Clinical Hospital) Dubrava, Zagreb, Croatia | 2004 |
237. | Vibration condition and behavior analysis of rotary furnace burner in GD Granit AD, Podružnica Zagreb, Asfaltna baza Okućani, Croatia | 2004 |
238. | Vibration condition and behavior analysis and balncing of turbine space airing fan pogona Etan, Ivanić Grad, INA-Naftaplina, Zagreb, Croatia | 2004 |
239. | Analysis of vibration condition and behavior od Unit 1 32 MW turbine and generator in TE-TOL Ljubljana, Slovenia | 2004 |
240. | Vibration condition analysis and balancing of electromotor rotor 90 kW for Mato el-d. Ivanić Grad, Croatia | 2004 |
241. | Vibration condition and behavior analysis of suction fan train in laundry plant of KB Dubrava, Zagreb, Croatia | 2004 |
242. | Analysis of vibrational condition and behavior of turbogenerator 1 machines (gas turbine+gear box+generator) in Ethan plant Ivanić Grad, INA-Naftaplin, Croatia | 2004 |
243. | Balancing of electromotor rotor 55 kW for Mato el-d Ivanić Grad, Croatia | 2004 |
244. | Vibration condition and behavior analysis of compressor train C-801A in Ethan Plant of INA Naftaplina, Ivanić Grad, Croatia | 2004 |
245. | Vibration condition and behavior analysis of compressor train C-801B in Ethan Plant,INA Naftaplin, Ivanić Grad, Croatia | 2004 |
246. | Bently Nevada System 1 platform optimalization on 289 MW turbogenerator (Unit 4) in Power Plant Šoštanj, Slovenia | 2004 |
247. | Detailed analysis of vibration condition and behavior of 289 MW turbine and generator (Unit 4) Power Plant Šoštanj, Slovenia during staertups, various loads operatrions and shutdowns | 2004 |
248. | Analysis of vibration condition and behavior of turbogenerator 1 (gas turbine+gear box+generator) in Ethan Plant Ivanić Grad, INA-Naftaplin, Croatia | 2005 |
249. | Vibration condition and behavior analysis of 125 MW turbine and generator (Unit 1) in Power Plant Plomin during steady state operation, unloading and shutdown before overhaul | 2005 |
250. | Unit 1 feed water pump trains (2 pcs) vibration condition and behavior analysis in Power Plant Plomin, Croatia befor overhaul | 2005 |
251. | Vibration condition and behavior analysis of 32 MW turbogenerator (Unit 1) in TE-TOL Ljubljana, Slovenia with special analysis of front turbine bearing journal hig vibration problem | 2005 |
252. | Analysis of vibration condition and behavior of 320 MW turbogenerator (turbine+generator) in Power Plant Rijeka , Croatia, after overhaul | 2005 |
253. | Vibration condition and behavior analysis of Unit 4 115 MW turbogenerator machines (gas turbine+gear box+generator) in Power Plant Brestanica, Slovenia after on-site balancing | 2005 |
254. | Predictive maintenance program and base vibration analysis of machines in Plant Messer Kutin, Croatia | 2005 |
255. | Analysis of vibration condition and behavior and balansing of 100 MW turbine (Unit 3) in Power Plant Tuzla, B&H | 2005 |
256. | Analysis of vibration condition and modeling of measuring piping lines in Underground Gas Storage PSP Okoli, Okoli, Croatia | 2005 |
257. | Analysis of vibration condition of turbogenerator 1 (gas turbine+gear box+generator) in Ethan plant Ivanić Grad, INA-Naftaplin, Croatia | 2006 |
258. | Analysis of the high vibration amplitudes problem of 45 MW turbine (Unit 3) TE-TOL Ljubljana, Slovenia | 2006 |
259. | Analysis of the high vibration amplitudes problem of 125 MW (Unit 1) LP turbine and generator in Power Plant Plomin, Croatia | 2006 |
260. | Vibration condition and behavior analysis of 125 MW turbogenerator in Power Plant Plomin, croatia during steady state operation, unloading and shutdown before overhaul | 2006 |
261. | Vibration condition and behavior analysis of FCC's turbotrain TGB+B 2501 in NIS-refinery Rafinery Pančevo, Serbia | 2006 |
262. | Analysis of vibrational condition and behavior of Unit 3 45 MW turbogenerator during steady state and shut-down before overhaul in TETO Osijek, Croatia | 2006 |
263. | Vibration condition nalysis of booster primary compressor in DIOKI d.d, Zagreb during numerous start-ups, shut-downs and steady state operations | 2006 |
264. | Vibration condition and behavior analysis of Unit 2 210 MW turbogenerator machines in Power Plant Plomin, Croatia during steady state operation, load variations, shut-down and start-up | 2006 |
265. | Complex analysis of high relative shaft vibration amplitudes on first bearing journal on the HP turbine of the 125 MW turbogenerator in Power Plant Plomin, Croatia after overhaul | 2006 |
266. | Vibration condition and behavior analysis of blower C-17 A in Ethan Plant, INA-Naftaplin, Ivanic Grad, Croatia | 2006 |
267. | Analysis of high generator shaft vibration amplitudes of the 320 MW turbogenerator in Power Plant Rijeka, Croatia during shut-down | 2006 |
268. | Vibration condition and behavior analysis of 45 MW turbogenerator in TE-TO Osijek after overhaul and additional generator repairs | 2006 |
269. | Vibration condition and behavior analysis and balancing of a stone crusher in Šumber quarry, Labin, Croatia | 2006 |
270. | Vibration condition and behavior analysis and balancing of waste air suction fan in Sirela Bjelovar, Croatia | 2006 |
271. | Analysis of high generator's rotor vibration amplitudes on 320 MW turbogenerator in Power Plant Rijeka ,Croatia, during shutdown on 21.10.2006. | 2006 |
272. | Analysis of vibrational condition and behavior of 45 MW turbogenerator machines in TE-TO Osijek, Croatia, during start-up, loading and steady state operation on 26.11.2006. after generator repairs | 2006 |
273. | Vibration condition and behavior analysis of 125 MW turbogenerator (Unit 1) in Power Plant Plomin, Croatia during start-up and steady state after overhaul | 2006 |
274. | Complex analysis of high journal vibration on bearing no. 1 of 125 MW turbine in PP Plomin after overhaul | 2006 |
275. | Analysis of cause of increase of journal vibration on bearing no. 4 of 125 MW turbine in Power Plant Plomin, Croatia | 2006 |
276. | Vibrational behavior analysis of turbocharger C-17-A INA-Naftaplin, Etan, Ivanić Grad, during steady state operation on 26.07.2006. | 2006 |
277. | On site balancing of TESAB 1012-4 crusher in Šumber quarry | 2007 |
278. | Vibration condition and behavior analysis of GT1 turbogenerator in INA-Naftaplina, Etan, Ivanić Grad,Croatia on 10.05.2007. | 2007 |
279. | Vibration condition and behavior analysis of 125 turbogenerator in Power Plant Plomin from 05.04. till 04.05.07. and during stady state operation unloading and shutdown befor overhaul in 2007. | 2007 |
280. | Vibration condition and behavior analysis of rotating and reciprocating machines in Messer Kutina, Croatia | 2007 |
281. | Analysis of vibration condition and behavior analysis of Unit 5 345 MW turbogenerator machines in Power Plant Šoštanj, Slovenia, during stady state operation,unloading and shutdown before overhaul on 26/27. 04. 2007. | 2007 |
282. | On site balancing of cooling tower fan in Tang, Nova Gradiška, Croatia | 2007 |
283. | On site balancing of TESAB 1012-4 crusher in Šumber quarry, Croatia | 2007 |
284. | Vibration condition r analysis and on-site balancing of fan in KB Dubrava, Zagreb, Croatia | 2007 |
285. | Vibration conditionn and behavior analysis of rotating and reciprocating machines after repairs in Messer Kutina, Croatia | 2007 |
286. | Analysis od vibrational condition and behavior of 210 MW turbogenerator in Power Plant Plomin, Croatia, during steady state,unloading and shutdownn and startup in April 2007. | 2007 |
287. | Vibrational condition and behavior analysis of 125 MW turbogenerator in Power Plant Plomin, Croatia in period from overhaul till 26.02.2007. | 2007 |
288. | Vibrational condition analysis and on-site balancing of fan in KB Dubrava, Zagreb, Croatia | 2007 |
289. | Vibrational condition and behavior analysis of 125 MW turbogenerator in Power Plant Plomin, Croatia in period from 05.04. till 04.05.07. and during shutdown before overhaul in 2007. | 2007 |
290. | Vibrational condition and behavior analysis of 30 MW turbogenerator in INA-Refinery Sisak, Croatia with emphasis on middle bearing block high vibration amplitudes | 2007 |
291. | Vibrational behavior analysis of 5 MW turbogenerator in Radeče papir d.d. during steady state operation, unloading and shutdown on 10. and 11. 08. 2007. | 2007 |
292. | Detailed analysis of high bearing block no. 2 (rear turbine and front generator bearing) vibration amplitudes of a 30 MW turbogenerator in INA Refinery Sisak (72 measurement locations – turbine, generator, base plaste, foundations) with dana acquisition during 18 start-ups, shutdowns and turbogenerator loading | 2007 |
293. | Vibrational condition and behavior analysis and on-site balancing of fan in KB Dubrava, Zagreb, Croatia | 2007 |
294. | Vibrational condition and behavior analysis of 345 MW turbogenerator (Unit 5) in Power Plant Šoštanj, Slovenia, during start-up, loading and steady state operation after overhaul | 2007 |
295. | Vibrational condition and behavior analysis of 45 MW turbogenerator in TE-TO Osijek during start-up, loading and steady state operation after overhaul on 29.06.2007. | 2007 |
296. | Analysis of cause of Increased rear generator bearing (no. 7.) journal vibration on 125 MW turbogenerator in Power Plant Plomin, Croatia | 2007 |
297. | Analysis of very high vibration problem of exhaust gasses fan no. 2 of Unit 6 in Power Plant Tuzla, B&H. | 2007 |
298. | Vibrational condition and behavior analysis of 125 MW turbogenerator in Power Plant Plomin, Croatia during start-up and steady state operation after overhaul | 2007 |
299. | Vibrational condition nalysis of furnace filter fan in ITV, Raša, Croatia | 2007 |
300. | Vibrational condition and behavior analysis of 32 MW turbogenerator in TE-TOL Ljubljana, Slovenia, on 09.12.2007. before and after gear removal from front bearing block | 2007 |
301. | Vibrational condition and behavior analysis of Hyper compressor BC-101 on Polyethylen plant in Dina Petrokemija d.d. on 06.12.2007. | 2007 |
302. | Vibrational condition and behavior analysis of rotating and reciprocating machines after repairs in Messer Kutina, Croatia | 2007 |
303. | Cyclone fan on-site balancing in Rockwool Adriatic d.o.o, Croatia | 2007 |
304. | On site balancing of TESAB 1012-4 crusher in Šumber quarry, Croatia | 2007 |
305. | Vibrational condition and behavior analysis of 125 MW turbogenerator in Power Plant Plomin, Croatia with emphasis on high generator casing vibration | 2007 |
306. | Alignment, on-site balancing and vibration analysis of fan in KB Dubrava, Zagreb, Croatia | 2007 |
307. | Vibrational condition and behavior analysis of synthesis gas turbotrain (GT201 + C201+202) on Methanol plant in NAFTA Petrochem d.o.o. Lendava, Slovenia, during steady state operation on 21.01.2008. | 2008 |
308. | Vibrational condition and behavior analysis of 7 MW turbogenerator in Power plant of INA Maziva Rijeka, Croatia during steady state operation and shut-down on 27.01.2008. | 2008 |
309. | Vibrational condition and behavior analysis of sythesis gas turbotrain (GT201 + C201+202) in Methanol plant in NAFTA Petrochem d.o.o. Lendava, Slovenia, during steady state operation and disturbance from 04.02. till 11.02.2008. | 2008 |
310. | Vibrational condition and behavior analysis of Sundyne DPF-103A pump in Dina Petrokemija d.d., Omišalj, Croatia | 2008 |
311. | Vibrational behavior analysis of machines in Energetika plant in Nafta petrochem d.o.o. Lendava, Slovenija during steady state on 19.02.2008. | 2008 |
312. | Cooling tower fan balancing in Messer Croatia plin, Kutina, Croatia | 2008 |
313. | Vibrational behavior analysis and on-site balancing of a fan in KB Dubrava, Zagreb, Croatia | 2008 |
314. | Vibrational condition analysis of cooling tower fans, motors for feedwater pumps and turbogenerator gearbox of Energetika plant in Nafta petrochem d.o.o. Lendava, Slovenija during steady state on 06.03.2008. | 2008 |
315. | Vibrational condition and behavior and process state analysis of compressor 313-K-002 on Platforming 2 Plant in INA-Refinery Rijeka, Craotia during tests on 13.03.2008. | 2008 |
316. | On site balancing of TESAB 1012-4 crusher in Šumber quarry, Croatia | 2008 |
317. | Vibrational condition and behavior analysis of 125 MW turbogenerator in Power plant Plomin, Croatia during unloading and shut-down on 26.02.2008. | 2008 |
318. | Cooling tower fan balancing in Messer Croatia plin, Kutina, Croatia | 2008 |
319. | Vibrational condition and behavior analysis of wet gas compressor 323-GC-1 on FCC plant in Oil rafinery Rijeka during startup and steady state from 10. till 11.04. 2008. | 2008 |
320. | Vibrational condition and behavior analysis of wet gas compressor 323-GC-1 on FCC plant in INA-Refinery Rijeka, Croatia during startup and steady state operation from 14. till 17. 04. 2008. | 2008 |
321. | Vibrational condition and behavior and process state (thermodynamical) analysis of compressor 313-K-002 on Platforming 2 plant in INA-Refinery Rijeka, Croatia after overhaul and high vibration amplitudes problem elimination during April 2008. | 2008 |
322. | Vibrational condition and behavior analysis of 125 MW turbogenerator in Power Plant Plomin, Croatia during start-up, loading and full load operation | 2008 |
323. | Vibrational condition and behavior analysis of 200 MW turbogenerator (Unit 4) in Power Plant Tuzla, B&H, during steady state and shut-down on 05.06.2008. | 2008 |
324. | Vibrational condition analysis of climatization fans York in Selk d.d. Kutina, Croatia | 2008 |
325. | Analysis of vibrational condition and behavior of GT1 turbogenerator (gas turbine+gear box+generator) on 27.06.2008. in INA Naftaplin d.d., Ethan Plant, Ivanić Grad, Croatia | 2008 |
326. | Vibrational condition analysis of Jung grinder no. 3 on Siemens line in Selk d.d. Kutina, Croatia during idle operation and gridning after motor replacement | 2008 |
327. | On site balancing of TESAB 1012-4 crusher in Šumber quarry, Croatia | 2008 |
328. | Laser flattness measurement and vibration state analysis of grinders Jung 2 and 3 on line Siemens in Selk d.d. Kutina, Croatia during idle operation and grinding | 2008 |
329. | Vibrational condition and behavior analysis of 5 MW turbogenerator in Radeče papir d.d, Slovenia during steady state operation, shut-downs and start-ups on 08.08.2008. | 2008 |
330. | Vibrational condition and behavior analysis of Hyper compressor BC-101 on Polyethylen Plant in Dina Petrokemija d.d. Omišalj, Croatia | 2008 |
331. | Laser flattness measurement and vibration state analysis of grinders Jung 1 and 2 on line Siemens in Selk d.d. Kutina, Croatia during idle operation and grinding | 2008 |
332. | Vibrational condition and behavior analysis of pump no. 2 branch no. 2 in boiler room and cooling pumpe EFG-2 in KB Dubrava, Zagreb, Croatia | 2008 |
333. | Vibrational condition and behavior analysis of gas motor and recip compressor IR KVR A inEthan Plant, Ivanić Grad, Croatia during steady state and speed variation on 14.07.2008. | 2008 |
334. | Vibrational condition analysis of two pumps in KB Dubrava, Zagreb, Croatia | 2008 |
335. | Vibrational condition and behavior analysis and on-site balancing of crusher in quarry Sv. Mikula, Coratia | 2008 |
336. | Vibrational behavior analysis of crack gas compressor on Ethylen Plant in HIP Petrohemija Pančevo, Serbia during steady state operation, unloading and shut-down for overhaul | 2008 |
337. | Vibrational behavior analysis of Prophylen cooling compressor on Ethylen Plant in HIP Petrohemija Pančevo, Serbia during steady state operation, unloading and shut-down for overhaul | 2008 |
338. | Vibrational behavior analysis of ethylen compressor on Ethylen Plant in HIP Petrohemija Pančevo, Serbia during steady state operation, unloading and shut-down for overhaul | 2008 |
339. | Vibrational behavior analysis of prophylen cooling compressor on Ethylen Plant in HIP Petrohemija Pančevo, Serbia during start-up,loading and steady state operation after overhaul | 2008 |
340. | Vibrational behavior analysis of ethylen compressor on Ethylen Plant in HIP Petrohemija Pančevo, Serbia during start-up,loading and steady state operation after overhaul | 2008 |
341. | Vibrational behavior analysis of crack gas compressor on Ethylen Plant in HIP Petrohemija Pančevo, Serbia during start-up,loading and steady state operation after overhaul | 2008 |
342. | Thermodynamic evaluation of GT-201 turbine and compressors G-201+G-202 of synthesis compressor train on Methanol plant, Nafte-petrochem Lendava, Slovenia | 2008 |
343. | Very high vibration amplitude analysis on a 12 MW turbogenerator in Refinery Bosanski Brod, R. Srpska, B&H | 2008 |
344. | Vibrational condition and behavior analysis of 30 MW turbogenerator in INA- Refinery Sisak, Croatia after middle bearing block modification | 2009 |
345. | Vibrational condition and behavior analysis of turbogenerator GT-1 (gas turbine,+gear box+generator) in Ethan Plant, Ivanić Grad, Croatia | 2009 |
346. | Vibrational condition and behavior analysis of 30 MW turbogenerator in INA- Refinery Sisak during tests after mechanical checks with emphasis on middle bearing block | 2009 |
347. | Vibrational condition r analysis of gridner Jung 1 on Siemens line after repairs in Selk d.d. Kutina, Croatia | 2009 |
348. | Vibrational condition analysis of climate fans York AHU-1 i AHU-2 in Selk d.d. Kutina, Croatia after repairs | 2009 |
349. | Vibrational condition analysis and balancing of funrace fan in Tang d.d. Nova Gradiška, Croatia | 2009 |
350. | Vibrational condition and behavior analysis of electromotors for mills and fans in Power Plant Ugljevik, R. Srpska, B&H | 2009 |
351. | Vibrational condition analysis of screw compressor 375-K-301 on PSA plant in INA-Refinery Rijeka, Croatia | 2009 |
352. | Vibrational condition and behavior analysis of new generator for Ethan Plant during tests in Končar-Generatori i motori d.d, Croatia | 2009 |
353. | Vibrational condition and behavior analysis of blower 323-FC-1 (turbine+blower) of FCC Plant in INA-Refinery Rijeka during start-ups, shut-downs and steady state operation | 2009 |
354. | Vibrational condition and behavior analysis of of wet gas compressr 323-GC-1 of FCC Plant in INA-Refinery Rijeka during start-ups, shut-downs and steady state operation | 2009 |
355. | Vibrational condition analysis of grinder Jung 4 on Siemens line during grinding before and after dress role replacement in Selk d.d. Kutina, Croatia | 2009 |
356. | Vibrational condition and behavior analysis of 300 MW turbogenerator (steam turbine+generator) in Power Plant Ugljevik during steady state and unplanned shut-down before overhaul in 2009, R. Srpska, B&H | 2009 |
357. | Vibrational condition and behavior analysis of pumping stations machines in PP Ugljevik, R. Srpska, BiH | 2009 |
358. | Vibrational condition and behavior analysis of compressor train 313-K-002 machines of Platforming 2 Plant before overhaul, INA-Refinery Rijeka, Croatia | 2009 |
359. | Vibrational condition and behavior analysis of 125 MW turbogenerator (turbine+generator) during steady state, unloading and shut-down before overhaul in 2009, Power Plant Plomin, Croatia | 2009 |
360. | Vibrational condition and behavior analysis of 125 MW turbogenerator during start-up, generator protection testing, loading and steady state operation after overhaul in 2009, Power Plant Plomin, Croatia | 2009 |
361. | Vibrational condition and behavior analysis of 125 MW turbogenerator during start-ups, synchronizations, loading and steady state after overhaul in 03.09.2009, Power Plant Plomin, Croatia | 2009 |
362. | Vibrational condition and behavior analysis of drying fan during balancing, Dukat d.d, Plant Sirela, Bjelovar, Croatia | 2009 |
363. | Vibrational condition and behavior analysis of Platforming Plant-2 turbotrain (turbine+compressor) 313-K-002 after overhaul, INA-Refinery Rijeka, Croatia | 2009 |
364. | Analysis of ibrational condition and behavior of left and right exhaust gas fans of Unit 5 in Power Plant Kakanj, B&H | 2009 |
365. | Vibrational condition and behavior analysis of 120 MW turbogenerator during steady state operation, unloading and shut-down before overhaul in 2009, TE TO Zagreb, Croatia | 2009 |
366. | Analysis of vibrational condition and behavior of 120 MW turbogenerator during start-up, generator protection testing, loading and steady state operation after overhaul in 2009, TE TO Zagreb, Croatia | 2009 |
367. | Vibrational condition and behavior analysis of FCC Plant blower 327 KA-001 machines after turbine and compressor overhaul in INA-Refinery Rijeka, Croatia | 2010 |
368. | Analysis of vibration condition and behavior analysis of 30 MW turbogenerator in INA-Refinery Sisak Power plant with on-site balancing, Croatia | 2010 |
369. | Analysis of vibrational condition and behavior of 42 MW turbine and generator (Unit 3) in TE-TOL Ljubljana, Slovenia | 2010 |
370. | Vibrational condition and behavior analysis of grinder Jung 3 in SELK Kutina, Croatia | 2010 |
371. | On-site balancing of fan with vibration anlalysis in TANG, Nova Gradiška, Croatia | 2010 |
372. | Vibrational condition and behavior analysis of 210 MW turbogenerato (Unit 7) during start-up, steady state operation and shut-down before overhaul, Power Plant Kakanj, B&H | 2010 |
373. | Vibrational condition and behavior analysis of crack gas compressor CT+C-201 on Ethylen plant, DIOKI d.d. Zagreb, Croatia | 2010 |
374. | Analysis of vibrational condition and behavior of 1,9 MW turbogenerator Siemens in Novoles d.d. Straža, Slovenia before major overhaul of turbine and gearbox in August 2010. | 2010 |
375. | Analysis of vibrational condition and behavior of 1,9 MW turbogenerator Siemens in Novoles d.d. Straža, Slovenia after major overhaul of turbine and gearbox in August 2010. | |
376. | Vibrational condition and behavior analysis of 30 MW turbogenerator during startup, trial run, loading and steady state operation, INA_Refinery Sisak, Croatia | 2010 |
377. | Analysis of vibrational condition and behavior 210 MW turbogenerator (Unit 7) during start-ups, steady state operations and shut-downs after overhaul, Power Plant Kakanj, B&H | 2010 |
378. | Vibrational condition and behavior analysis of machines in KTE Jertovec, Croatia before overhaul in 2010. | 2010 |
379. | Vibrational condition and behavior analysis of 12 MW turbogenerator in EL-TO Zagreb, Croatia during startups, synchronization, tests, shutdowns, loading and steady state operation after overhaul | 2010 |
380. | Vibrational condition and behavior analysis of 30 MW turbogenerator in EL-TO Zagreb, Croatia during startups, synchronization, tests, shutdowns, loading and steady state operation after overhaul | 2010 |
381. | Vibrational condition and behavior analysis of screw compressor 375-K-301 on PSA plant in INA-Refinery Rijeka, Croatia during tests in August and September 2010. | 2010 |
382. | On-site balancing of 4 in KTE Jertovec, Croatia | 2010 |
383. | Vibrational condition and behavior analysis of air compressor no. 2 in compressor station in U.S. Steel Smederevo, Serbia | 2010 |
384. | Vibrational condition and behavior analysis of air compressor no. 3 in compressor station in U.S. Steel Smederevo, Serbia | 2010 |
385. | Analysis ofvibrational condition and behavior and analysis of governing system of 45 MW turbogenerator during tests on 29. and 30. 12. 2010, TE-TO Osijek, Croatia | 2010 |
386. | Analysis of FCC Plant turbotrain 327-K-001 high vibration problem analysis, INA-Refinery Rijeka, Croatia | 2011 |
387. | Speed oscillation problem analysis of FCC Plant compressor 328-K-001, INA-Refinery Rijeka, Croatia | 2011 |
388. | Analysis of high vibration amplitudes problem on 376 P 002B pump, Hydrocracker Plant, Oil rafinery Rijeka, Croatia | 2011 |
389. | Analysis of problem with governing system of 20 MW steam turbine in INA-Refinery Rijeka, Croatia during tests in January 2011. | 2011 |
390. | Vibrational condition and behavior analysis of machines (two 31,5 MW gas turbogenerator, 12,5 MW steam turbogenerator, 3 feed water pumps trains, 4 cooling water pumps trains, 2 fans) in KTE Jertovec, Croatia after overhaul in 2010/2011. | 2011 |
391. | Analysis of vibrational condition and behavior of pilot plant turbogenerator ĐĐ-ENITEH 500, Đuro Đaković Elektromont, Slavonski Brod, Croatia | 2011 |
392. | Balancing of fans of pilot plant ĐĐ-ENITEH 500, Đuro Đaković Elektromont, Slavonski Brod, Croatia | 2011 |
393. | Vibrational condition and behavior analysis of oxygen compressr KTK-2, Messer Tehnogas AD, Smederevo, Serbia | 2011 |
394. | Vibrational condition and behavior analysis of rotating and reciprocating machines in Messer Kutina, Croatia during steady state opeartion on 18.04.2011. | 2011 |
395. | Vibrational condition and behavior analysis and analysis of governing system of 45 MW turbogenerator during tests in June 2011, TETO Osijek, Croatia | 2011 |
396. | Vibrational condition and behavior analysis of TG 2 turbogenerator in KTE Jertovec, Croatia during start-up, loading and steady state operation on 18.07.2011. | 2011 |
397. | Vibrational condition and behavior analysis of 348 MW turbogenerator (Unit 6) in Power Plant Nikola Tesla A, Obrenovac, Serbia during startup on 02.12.2011. and steady state operation from 2nd till 9th December 2011 | 2011 |
398. | Analysis of vibration condition and behavior of 75 MW steam turbine and generator (Unit 3) in Power Plant Šoštanj, Slovenia | 2012 |
399. | Analysis of vibration condition and behavior of 210 MW steam turbine and generator (Unit 2) before overhaul in Power Plant Plomin, Croatia | 2012 |
400. | Analysis of vibration condition and behavior of 210 MW steam turbine and generator (Unit 2) after overhaul in Power Plant Plomin, Croatia | 2012 |
401. | Vibrational condition and behavior analysis of 75 MW steam turbine and generator (Unit 3) after rotor repairs in Power Plant Šoštanj, Slovenia | 2012 |
402. | Vibration condition and behavior analysis of Air Blower 379-KA-101, air suply line, air heater 379-E-102 and furnace 379-H (furnace and burners) with furnace and thermoacoustic analysis in SRU plant in INA-Refinery Rijeka, Croatia | 2012 |
403. | Vibration condition and behavior analysis of 115 MW gas turbine, gearbox and generator (Unit 4) before overhaul in Power Plant Brestanica, Slovenia | 2012 |
404. | Vibration condition and behavior analysis of 115 MW gas turbine, gearbox and generator (Unit 4) after overhaul in Power Plant Brestanica, Slovenia | 2012 |
405. | Analysis of vibration condition and behavior of GB-5001 (electromotor, gearbox and compressor) on the new Hydrocracking Plant during commisioning in NIS-Refinery Pančevo, Serbia | 2012 |
406. | Analysis of vibration condition and behavior of GB-2453 B (booster blower) on the new Hydrocracking Plant during commisioning in NIS-Refinery Pančevo, Serbia | 2012 |
407. | Analysis of vibration condition and behavior of R-1 turbotrain (crack gas compressor) during startup, loading and steady state operation after overhaul, Ethylen Plant in HIP Petrohemija Pančevo, Serbia | 2012 |
408. | Analysis of vibration condition and behavior of R-2 turbotrain during startup, loading and steady state operation after overhaul, Ethylen Plant in HIP Petrohemija Pančevo, Serbia | 2012 |
409. | Analysis of vibration condition and behavior of R-3 turbotrain during startup, loading and steady state operation after overhaul, Ethylen Plant in HIP Petrohemija Pančevo, Serbia | 2012 |
410. | Vibration condition and behavior analysis of buthadien screw compressor train CM-1140 (electromotor+gearbox+compressor) in FSK Elemir (Synthetic Rubber Plant), Serbia | 2013 |
411. | Vibration condition and behavior analysis of 39 fans and electromotors, Underground Gas Storage PSO Okoli, Croatia | 2013 |
412. | Analysis of vibration condition and behavior of FCC Plant's turbotrain GB-2301, from 18.11.2012. to 10.06.2013. (steady state operation, shudowns and startups) , NIS-Refinery Pančevo, Serbia | 2013 |
413. | Analysis of vibration condition and behavior of FCC Plant's turbotrain GB-2501, from 18.11.2012. to 10.06.2013. (steady state operation, shudowns and startups), NIS-Refinery Pančevo, Serbia | 2013 |
414. | Analysis of vibration condition and behavior of Alkyne Plant's turbotrain GB-2601, from 18.11.2012. to 10.06.2013. (steady state operation, shudowns and startups), NIS-Refinery Pančevo, Serbia | 2013 |
415. | Analysis of thermodynamic and operation condition and behavior of FCC Plant's turbotrain GB 2301, NIS-Refinery Pančevo, Serbia | 2013 |
416. | Analysis of thermodynamic and operation condition and behavior of FCC Plant's turbotrain GB 2501, NIS-Refinery Pančevo, Serbia | 2013 |
417. | Analysis of thermodynamic and operation condition and behavior of Alkyne Plant's turbotrain GB 2601, NIS-Refinery Pančevo, Serbia | 2013 |
418. | Study on replacement of FCC and Alkyne Plants' steam turbines with electromotors, NIS-Refinery Pančevo, Serbia | 2013 |
419. | Vibration condition analysis of main and auxiliary machinery (two 31,5 MW gas turbogenerator, 12, MW steam turbogenerator, 3 feed water pumps trains, 4 cooling water pumps trains, 2 fans), KTE Jertovec, Croatia | 2013 |
420. | Vibration condition and behavior analysis of Ethylen Plant's turbotrain R-1 in HIP Petrohemija Pančevo, Serbia | 2013 |
421. | Vibration condition and behavior analysis of steam turbine and compressor (Nuovo Pignone) 327-KA-001 on FCC Plant after the major overhaul, INA-Refinery Rijeka, Croatia | 2013 |
422. | Vibration behavior analysis of steam turbine and compressor (Nuovo Pignone) 313-K-002 on Platforming 2 Plant after the major overhaul, INA-Refinery Rijeka, Croatia | 2013 |
423. | Vibration condition analysis of fan, Plant Sirela, Dukat d.d., Croatia | 2013 |
424. | Vibrational condition and behavior analysis of rotary screw compressor train HIP- Petrohemija Pančevo, Serbia | 2014 |
425. | Vibration condition and behavior analysis of turbotrain PT5116 (1,2 MW steam turbine +gear box +pump), KP4 Plant, INA-Refinery Sisak, Croatia | 2014 |
426. | Vibration condition analysis of 4 Water Pumps (electro motor and pump) in Moslavina d.o.o., Kutina, Croatia | 2014 |
427. | Vibration condition analysis of 12 fans (electro motor+ belt drive+ fan) in Selk d.d. Kutina, Croatia | 2014 |
428. | Analysis of the air compressors 379-K-101 A i B operation and vibrational condition with special stress on antisurge system operation, INA-Refinery Rijeka, Croatia | 2014 |
429. | Vibration condition and behavior analysis of Fan, Rockwool Adriatic d.o.o., Croatia | 2014 |
430. | Analysis of operation and configuration of the governing systems on three turbotrains R-1, R-2 and R-3 (De Laval 14,34 MW, 11,76 MW and 1,73 MW), Ethylene Plan HIP-petrokhemija Pančevo, Serbia | 2014 |
431. | Vibrational condition and behavior analysis of rotary screw compressor trains NH3 and CO2 in Messer Croatia Gas, Croatia | 2014 |
432. | Vibrational condition analysis of Pump (P-7402: Electromotor+ Gear Box+ Pump) in JANAF (crude oil transportation and storage of oil and oil products), Croatia | 2014 |
433. | Vibrational condition analysis of rotary screw compressor trains NH3 and CO2 in Messer Croatia Gas, Croatia | 2015 |
434. | Vibrational condition and behavior analysis of Fan (electric motor+ belt drive +fan) in the dairy industry Dukat Sirela in Bjelovar, Croatia | 2015 |
435. | Vibrational condition and behavior analysis of oil transport pump P-2603 (electric motor, Voith transmission with a hydrodynamic coupling and pump) in JANAF (crude oil transportation and storage of oil and oil products), Croatia | 2015 |
436. | Vibrational condition and behavior analysis of oil transport pump P-7106 (electric motor, Voith transmission with a hydrodynamic coupling and pump) in JANAF (crude oil transportation and storage of oil and oil products), Croatia | 2015 |
437. | Vibrational condition and behavior analysis of Pump RCP (reactor cooling pump train) 1, Nuclear Power Plant Krško, Slovenia | 2015 |
438. | Analysis of reasons of wet gas compressor 328-K-001 forced shutdowns in FCC Plant INA-Refinery Rijeka during startups in February 2015, Croatia | 2015 |
439. | Analysis of reasons of wet gas compressor 328-K-001 forced shutdowns in FCC Plant INA-Refinery Rijeka in February – April 2015,, Croatia | 2015 |
440. | Analysis of vibration condition and behavior of Platforming Plant-2 turbotrain 313-KA-002 in INA-Refinery Rijeka, Croatia, after disturbances caused by Plant's fire | 2015 |
441. | Analysis of the high vibraton problem of Unit 7 indiced draft fan, Thermal Power Plant Kakanj, Bosnia and Hercegovina | 2015 |
442. | Vibration condition and behavior analysis of fline of fans (electro motor+ belt drive+ fan) in Selk d.d. Kutina, Croatia | 2016 |
443. | Vibration behavior analysis of machine WAC715 SCALAR (Wendt GmbH) with a stress on efficency increasing using new components of the machine in Selk d.d. (EPCOS) Kutina, Croatia | 2016 |
444. | Vibration condition and behavior analysis of Ammonia Plant's turbotrain TC+SM+C 21101 (steam turbine, LP compressor, gear box and HP compressor) during startup, loading and steady state operation after overhaul, Petrokemija Kutina, Croatia | 2016 |
445. | Analysis of vibration condition and behavior of Ammonia Plant's TC+C 21105 turbotrain (steam turbine, LP compressor and HP compressor) during startup, loading and steady state operation after overhaul, Petrokemija Kutina, Croatia | 2016 |
446. | Analysis of vibration condition and behavior of Urea Plant's turbotrain TC+C+SM 22112 (steam turbine, LP compressor, gear box and HP compressor) during startup, loading and steady state operation after overhaul, Petrokemija Kutina, Croatia | 2016 |
447. | Analysis of vibration condition and behavior of 20 MW turbogenerator during startup and idle operation without synchronization after major overhaul in Energana II Power Plant, INA-Refinery Rijeka, Croatia | 2016 |
448. | Analysis of vibration condition and behavior of 20 MW turbogenerator during startup,idle operation,synchronization, loading and steady state operation after major overhaul in Energana II Power Plant, INA-Refinery Rijeka, Croatia | 2016 |
449. | Vibrational condition and behavior analysis of oil transportation pump P-7106 (electric motor, Voith transmission with a hydrodynamic coupling and pump) in JANAF (crude oil transportation and storage of oil and oil products), Croatia | 2016 |
450. | Analysis of FCC Plant's GB 2301 turbotrain possibility to work bellow minimal governing speed, NIS-Refinery Pančevo, Serbia | 2016 |
451. | Vibrational condition and behavior analysis of off-line rotating equipment (few hundreds ofelectromotors, pumps, fans,...) in INA-Refinery Rijeka, Croatia | 2016 |
452. | Vibrational condition and behavior analysis in April of off-line rotating equipment (few hundreds ofelectromotors, pumps, fans,...) in INA-Refinery Rijeka, Croatia | 2017 |
453. | Analysis of 20 MW turbogenerator (341-TA-021) cause of forced and unplanned shutdown and vibration condition and behavior, Power Plant-2, INA-Refinery Rijeka, Croatia | 2017 |
454. | Analysis of 20 MW turbogenerator (341-TA-021) vibration condition and behavior during startup, excessive overspeed operation and shutdown, Power Plant-2, INA-Refinery Rijeka, Croatia | 2017 |
455. | Complex analysis of 3 MW steam turbine rear bearing high vibration problem with evaluation of steam turbine, gear box and generator condition in BE-TO (Biomass Power Plant) Osijek, Croatia | 2017 |
456. | Vibrational condition and behavior analysis in Julyl of off-line rotating equipment (few hundreds ofelectromotors, pumps, fans,...) in INA-Refinery Rijeka, Croatia | 2017 |
457. | Analysis of 500 kW turbogenerator gear box very high shaft vibration amplitudes in Thermal Power Plant Miljöteknik Energi AB, Ronneby, Sweden | 2017 |
458. | Vibrational condition and behavior analysis in October of off-line rotating equipment (few hundreds ofelectromotors, pumps, fans,...) in INA-Refinery Rijeka, Croatia | 2017 |
459. | Analysis 3 MW steam turbine turbogenerator (steam turbine, gear box and generator) vibration condition and behavior after stiffness modification, BE-TO (Biomass Power Plant), Osijek, Croatia | |
460. | Vibrational behavior analysis of oil transport pump (electric motor 2,5 MW, Voith transmission with hydrodynamic coupling and pump) in JANAF (crude oil transportation and storage of oil and oil products), Croatia | 2017 |
461. | Vibrational behavior analysis of oil transport pump (electric motor 2,0 MW and pump) in JANAF (crude oil transportation and storage of oil and oil products), Croatia | 2017 |
462. | Vibrational condition and behavior analysis of Francis Hydroturbine 155 MW in Shiroro/Abuja, Nigeria | 2017 |
463. | Analysis of MK-5 reciprocating compressor and electromotor vibration and process (thermodinamical) condition and behavior during commissioning and operation, PSP Okoli (Underground gas storage), Croatia | 2017 |
464. | Vibrational condition and behavior analysis of oil transport pump (electric motor 3,3 MW, Voith transmission with hydrodynamic coupling and pump) in August after pump major overhaul (crude oil transportation and storage of oil and oil products), JANAF Omišalje, Croatia | 2017 |
465. | Analysis of vibiration condition and behavior of 45 MW turbogenerator (Unit 3) in TE-TO Ljubljana, Slovenia during startup, loading and steady state operation on 09.11.2017. after overhaul | 2017 |
466. | Vibrational condition and behavior analysis of oil transport pump (electric motor 3,3 MW, Voith transmission with hydrodynamic coupling and pump) in September after mechanical corrective works (crude oil transportation and storage of oil and oil products), JANAF Omišalje, Croatia | 2017 |
467. | Vibrational condition and behavior analysis of induced draft fanof Unit 7 (210 MW), Thermal Power Plant Kakanj, Bosnia and Hercegovina | 2017 |
468. | Analysis of MK-5 reciprocating compressor and electromotor vibration and process (thermodinamical) condition and behavior during commissioning and operatio, PSP Okoli (Underground gas storage), Croatia | 2017 |
469. | Analysis of MK-5 reciprocating compressor and electromotor vibration and process (thermodinamical) condition and behavior during normal operation, PSP Okoli (Underground gas storage), Croatia | 2017 |
470. | Analysis of Termoelektrarna Brestanica, Slovenia GT 26 Turbogenerator Machines (gas turbine+gear box+generator) vibrational behavior and condition during Testing in March 2018 | 2018 |
471. | Analysis of the Ammonia Plant'a air compressor turbotrain gear box SM 21101 high vibration problem and damage, Petrokemija kutina, Croatia | 2018 |
472. | Analysis of the Ammonia Plant'a air compressor turbotrain gear box SM 21101 vibiration condition and behavior before and after repair, Petrokemija kutina, Croatia | 2018 |
473. | Analysis of the Ammonia Plant'a air compressor turbotrain gear box SM 21101 casing vibration condition and behavior after repair, Petrokemija Kutina, Croatia | 2018 |
474. | Analysis of 730 MW turbogenerator vibrational condition and behavior before exciter replacement, Nuclear Power Plant Krško, Slovenia | 2018 |
475. | Analysis of thermodynamic and operational condition and behavior of FCC Plant's wet gas compressor (GB 2501) with recomendations for corrective actions and assistence in execution, NIS-Refinery Pančevo, Serbia | 2018 |
476. | Analysis of vibration condition and behavior of Ammonia Plant's turbotrain TC+SM+C 21101 (steam turbine, LP compressor, gear box and HP compressor) before overhaul, Petrokemija Kutina, Croatia | 2018 |
477. | Analysis of vibration condition and behavior of Ammonia Plant's turbotrain (natural gas compressor) TC+ C 21102 (steam turbine+compressor) before overhaul, Petrokemija Kutina, Croatia | 2018 |
478. | Analysis of vibration condition and behavior of Ammonia Plant's turbotrain (synthesis gas compressor) TC+C 21103 (steam turbine, LP compressor and HP compressor) before overhaul, Petrokemija Kutina, Croatia | 2018 |
479. | Vibration condition and behavior analysis of Ammonia Plant's turbotrain (ammonia refrigerant compressor) TC 21105 (steam turbine, LP compressor and HP compressor) before overhaul, Petrokemija Kutina, Croatia | 2018 |
480. | Vibration condition and behavior analysis of Urea Plant's turbotrain TC+SM+C 22112 (steam turbine, LP compressor, gear box and HP compressor) before overhaul, Petrokemija Kutina, Croatia | 2018 |
481. | Vibration condition and state analysis of newly installed Termomeccanica Pompe in Janaf, Croatia | 2018 |
482. | Analysis of vibration condition and behavior of train P-7107 (electromotor, Voith coupling/gearbox,pump) in Terminal Omišalj, Janaf, Croatia after electromotor replacement and Voith coupling overhaul | 2018 |
483. | Analysis of vibration condition of conveyers' drivers CP-101 CV-103 and CV-104 in Port Ploče, Croatia | 2018 |
484. | Vibration condition and behavior analysis of Ammonia Plant's turbotrain (air compressor) TC+SM+C 21101 (steam turbine, LP compressor, gear box and HP compressor) during startup, loading and steady state operation after overhaul, Petrokemija Kutina, Croatia | 2018 |
485. | Vibration condition and behavior analysis of Ammonia Plant's turbotrain (natural gas compressor) TC+ C 21102 (steam turbine+compressor) during startup, loading and steady state operation after overhaul, Petrokemija Kutina, Croatia | 2018 |
486. | Vibration condition and behavior analysis of Ammonia Plant's turbotrain (synthesis gas compressor) TC+C 21103 (steam turbine, LP compressor and HP compressor) during startup, loading and steady state operation after overhaul, Petrokemija Kutina, Croatia | 2018 |
487. | Vibration condition and behavior analysis of Ammonia Plant's turbotrain (ammonia refrigerant compressor) TC 21105 (steam turbine, LP compressor and HP compressor) during startup, loading and steady state operation after overhaul, Petrokemija Kutina, Croatia | 2018 |
488. | Vibration condition and behavior analysis of Urea Plant's turbotrain TC+SM+C 22112 (steam turbine, LP compressor, gear box and HP compressor) during startup, loading and steady state operation after overhaul, Petrokemija Kutina, Croatia | 2018 |
489. | Analysis of vibrational condition and behavior of turbotrain TC+SR 52101 after overhaul, PEPI Plant, Petrokemija Kutina, Croatia | 2018 |
490. | Analysis of high vibration problem of air compressor in Oxygen Plant, ABS d.o.o. Sisak, Croatia | 2018 |
491. | Analysis of vibration and process (thermodynami) condition and behavior of MK-1 train (gas engine+reciprocating compresor) during commissioning, PSP Okoli (Underground gas Storage), Croatia | 2018 |
492. | Analysis of vibration and process (thermodynami) condition and behavior of MK-2 train (gas engine+reciprocating compresor) during commissioning, PSP Okoli (Underground gas Storage), Croatia | 2018 |
493. | Analysis of vibration and process (thermodynami) condition and behavior of MK-1 train (gas engine+reciprocating compresor) during normal operation, PSP Okoli (Underground gas Storage), Croatia | 2018 |
494. | Analysis of vibration and process (thermodynami) condition and behavior of MK-2 train (gas engine+reciprocating compresor) during normal operation, PSP Okoli (Underground gas Storage), Croatia | 2018 |
495. | Complex analysis of the longlasting problem with Urea Plant's HP compressor high vibration and operational problems, as well as problem with shaft currents, Petrokemija Kutina, Croatia | 2018 |
496. | Complex analysis of high shaft vibration amplitudes of TA 3's 16 MW generator during startups and operation after overhaul, DS Smith Belišće Croatia d.o.o., Croatia | 2018 |
497. | Analysis of vibration condition of a new Turboden turbogeneratoru on a geothermal plan Velika Ciglena during comissioning testing on 21.01.2019. | 2019 |
498. | Complex analysis of high shaft vibration amplitudes of TA 2 turbogenerator after overhaul, DS Smith Belišće Croatia d.o.o., Croatia | 2019 |
499. | Vibration analysis of new pumps delivered by Termomeccanica Pompe on crude oil terminal Omišalj, Janaf | 2019 |
500. | Vibration analysis of GB 4301 turbotrain in Oil Refinery Pančevo, Serbia | 2019 |
501. | Crude oil pump P-7107 on terminal Omišalj after motor replacemetn, Janaf, Hrvatska | 2019 |
502. | Vibration analysis of hydrogen compressor GB-5001, Hydrogen plant, Oil Refinery Pančevo, Srbija | 2019 |
503. | Vibration analysys of compressor trains 327-K-001, 376-K-001 and 313-K-002 after overhaul, Oil Refinery Rijeka | 2019 |
504. | Vibration analysis of hydropowerplant turbogenerator in MHE Melje, Slovenia | 2019 |
505. | Vibration analysis of blower C for fluidized bed in Powerplant Stanari, BiH | 2019 |
506. | Vibration analysis of CNC machines Jung J1 and J3 in Selk d.d. Kutina | 2020 |
507. | Vibration analysis of new pump 6320 delivered by Termomeccanica Pompe on crude oil terminal Omišalj after redesign, Janaf | 2020 |
508. | Building elevator drive analyisis in Zagreb | 2020 |
509. | Complex analysis of high shaft vibration amplitudes of TA 2 turbogenerator, DS Smith Belišće Croatia d.o.o., Croatia | 2020 |
1. These references of diagnostic works states only works that were carried by Turbomehanika experts as Turbomehanika employees. Most of the analysis required to analyse more machines since the entire trains were analysed.
2. Before 1994. our experts carried out few hundreds analysis on machines in Petrokemija Kutina, Croatia (that had first Bently Nevada computerized diagnostics system in Europe in early 1980's that monitored 6 turbotrains) where they used to do predictive maintenance by using both on-line and periodic (ADRE) measurement.
3. Turbomehanika is authorized partner and distributor of General Electric Company for Bently Nevada products. Bently Nevada is world leading manufacturer of equipment for monitoring, protection and diagnostics of machinery.
4. Turbomehanika's experts use for DAQ and diagnostics the following equipment:
a. Portable data collector 408 SXP (24 channels + digital recorder)
b. Portable data collectors Bently Nevada DAIU 208-P (16 channels)
c. Mini rack able to collect data from up to 60 channels
e. Software ADRE SXP
e. Software ADRE for Windows Bently Nevada
f. Software System 1 Bently Nevada
g. Software for balancing Turbobalans –Turbomehanika
h. Software for balancing Bently balans
i. Rotor-bearing system modeling software DYROBES
5. Turbomehanika installed a significant number of systems for monitoring, protection and diagnostics of machinery